Final two pandemic-delayed BTO projects completed: HDB

The standing projects had waiting times of up to five years. In general, over 18,000 apartments were finished in 2024, claims HDB.

Positioned throughout New Punggol Roadway, Punggol Point Cove (Phase 2) consists of 1,179 units of two-room flexi, 3-, 4- and five-room condos across 6 home blocks. Following pandemic problems, the work’s last block was finished one year from its initial Probable Completion Date (PCD) at an earlier time this month.

As at Jan 15, 657 households or 59% of 1,109 reserved units have gathered their keys.

As at Jan 15, 37 houses or about 7% of 555 booked units have collected their keys.

Currently, 110 HDB home jobs are under development, up from 95 a year ago due to the increase in BTO supply in recent years. HDB says it is on track to complete around 17,000 flats across 27 projects in 2025.

The 22 house projects consisted of two Shorter Waiting Time (SWT) projects, which were finished in just a waiting duration of less than three years. The SWT work, Parc Glen at Tengah and Grove Spring at Yishun, comprised a total amount of 1,995 apartments.

Coastal Cabana condo

Minister for National Development Desmond Lee has announced the finish of the last two pandemic-delayed projects from HDB, according to a Jan 20 release.

In 2024, HDB completed a total of 22 home ventures, 17 of which were postponed by the pandemic. With the exception of one that was delayed because of non-pandemic factors, the standing four housing projects were completed on time.

Situated around Serangoon Road, Lavender Street and Boon Kheng Road, Kempas Residences BTO project has 583 units of two-room flexi, three-, four-room flats across four residential blocks.

HDB is anticipated to alert the waiting flat owners of their key collection date shortly, following the completion of the final blocks just within both projects this month.

Both Build-to-Order (BTO) plans, Punggol Point Cove (Stage 2) and Kempas Residences, note the conclusion of HDB’s pandemic-delayed housing ventures. As a whole, the 92 plans have supplied over 75,800 new condos to Singaporeans over the last five years.

Condo proprietors of Punggol Point Cove (Phase 2) have actually been obtaining the keys to their brand-new home from November 2024, while key collection for Kempas Residence started in mid-January this year.

The final block, which was delayed by six months from its first PCD, was completed in mid-January.

According to HDB, the completion of Punggol Point Cove (Phase 2) denotes the completion of all flats in the Punggol Point District. This includes Punggol Point Cove (Stage 1), Punggol Point Woods and Punggol Point Crown BTO projects, that were finished in 2024.